e|agenda.NET Sarasota County Schools |
THE SCHOOL BOARD OF SARASOTA COUNTY, FLORIDA Landings Administrative Complex 1980 Landings Blvd. 3:00 P.M. |
Agenda Item #23 Title ACCEPTANCE OF SUBSTANTIAL COMPLETION FOR THE OAK PARK SCHOOL - HVAC RENOVATION: PHASE 3 Description This is one (1) of thirteen (13) phases of the project to achieve completion. The engineer has prepared the Certificate of Substantial Completion and the final punch list. This is only a portion of the contract and is substantially complete in accordance with the contract documents. A copy of the final punch list is available for review at the Construction Services Department. Recommendation That the work performed by Willis A. Smith Construction, Inc. for the Oak Park School - HVAC Renovation project: Phase 3 be accepted as substantially complete as of 9/20/2006. Contact LEMPE & COLLINS Financial Impact N/A Attachment: BAIenc10-17-06OakParkHVAC-Phase3SC.pdf |